Oct 25, 2017 | ,

4 Downey Drive, Manning – Project Update October 2017

The working drawings for the development were completed in the last week of September.  After a thorough review, the drawings were then certified and issued to five builders for pricing via a tender process.   

The tender submissions were received on Wednesday 25th October and it will take us approximately a week to analysis the submissions, negotiate terms and execute a building contract with the winning builder.

We are still confident of commencing construction before the end of November.

It was decided to delay the marketing campaign until after a building contract has been executed.  We are now aiming to commence the marketing campaign in mid to late November.  If you, or someone you know, are interested in talking to one of our sales agents about being one of the first to secure one of the apartments or townhouse I encourage you to call the office on (08) 6144 0700.

I look forward to updating you next month, but should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Travis McKenzie